Last Uploaded: December, 2009
Panasonic Electric Works Tokyo Headquarters building
Special Features
Q-1 Indoor Environment |
|
Q-2 Quality of Service |
- OA floor: 150 mm
- Power supply capacity: 60 VA/m²
- Ceiling height: 2.8 m
- Story height: 4.25 m
- Modular design (easy partition)
- Outdoor air cooling system
- Earthquake resistance level: 1.5 times the level required by the Building Standard Law
- Damper
- District cooling and heating system (highly reliable)
- District grey-water system
- Collected drainage treatment facility
|
Q-3 Outdoor Environment on Site |
- Roof greening
- Townscape coordination of the entire redeveloped block
- Restored station house within the same block (preserving historical buildings)
|
LR-1 Energy |
- PAL value: 283.6 MJ/m²/year
CEC/AC: 1.36, CEC/V: 0.84, CEC/L: 0.63, CEC/EV: 0.56
- Energy saving target: Approx. 20% higher than general buildings (2,115 MJ/m²/year)
- Natural daylighting, natural ventilation, and photovoltaic power generation systems were installed
- Conservation of energy at the operation stage: Metering of each air conditioning system and detailed metering of power consumption by power units, lighting, and outlets in each zone
- A dispersed type BEMS is installed
- Commissioning (performance verification) was conducted by the owner, the facility supervisor, the designer, and the constructor at the operation stage
|
LR-2 Resources and Materials |
- Water reclaimed by local infrastructure is used
- Collected drainage treatment facility
- Toilet flushing sound simulator and water-saving toilet bowls are used
- Kitchen garbage is composted
- CFC-free fire extinguishers
- Individual air conditioning system by using non-CFC refrigerant
- Wooden materials are used for a wood deck, etc.
|
LR-3 Off-site Environment |
- The heat island effect resulting from the use of local air conditioning is prevented
- Air pollution resulting from non-combustion appliances is prevented (hot water is supplied to kitchens by night storage type water heaters)
- Roof greening, wood deck and greening on the 24th floor
- West side lighting that takes into consideration light pollution in order to avoid disturbing neighboring buildings
- Noise and vibration-producing appliances are installed underground or measures to reduce noise are taken
|
Other Features
Outside air cooling system
Lighting/air conditioning/blind cooperative control system
These cases are described based on assessment results obtained using
CASBEE.
CASBEE is a method for rating the environmental performance of buildings using
Building Environmental Efficiency (BEE) as an indicator, which is based on the results of
separate scores obtained for Q-1~Q-3 (Quality) and LR-1~LR-3 (Load Reduction).